Schedule
Early Spring 2008
>> Work commences on access and link roads at Charing Cross, Byres Road and at the A739 entrance to the Clyde Tunnel.
Autumn 2008
>> Relocation of businesses on route.
>> Supporting ground works carried out in Kelvingrove Park.
Winter 2008/9
>> Work commences on main section of road.
Spring 2010
>> Road opens to the public.
|